Project Overview
The Town of Antigonish is working to improve Main Street between Haley Road and Marian Drive. These improvements include a full sanitary main and watermain replacement within a new utility corridor, street recapitalization, and the continuation of active transportation network.
It’s a large project and has been spilt into two phases.
Phase 1A
The tender for Phase 1 of the Bay Street Project was awarded to Dexter Construction for $2,182,315.00 + HST in the Fall of 2025.
From October to December 2025, construction was focused in the area between the bridge on the east end of Main Street (Haley Road) to the railway tracks.
- New water lines were installed from Haley Road to under the railway tracks and these new lines were connected to customers.
- New sewer lines were installed up to the railway tracks.
- The street between Haley Road and the tracks was raised for flood prevention.
- Prep work was done for new curb, sidewalks, and an active transportation trail.

Phase 1B
Mainly due to weather conditions (rain in November and multiple snowstorms in December), all the work for phase one was not completed as planned before the end of the year.
Work on this phase started in April 2026 with the removal of a few trees and new power poles being installed to move power lines needed to realign the street.
- Extending the new sewer line under the railway tracks
- Beginning Monday, April 20, traffic control will be in place each evening starting at 6 p.m. and will remain in effect overnight until 7 a.m. These nightly traffic measures will continue throughout the week and will conclude Friday morning (April 24).
- Pubic Notice
- New asphalt on the street and active transportation trail
- New concreate curbs and sidewalks
Phase Two
Phase two essentially picks up where phase one leaves off – at the railway tracks and continues up the hill to the hospital entrance at Marian Drive.
Similar to the first phase, new water and sewer lines will be installed, there will be the continuation of the active transportation trail with new curb and crosswalks. Phase two also include an updated rail crossing that will include a safer pedestrian crossing.
Once complete, this corridor will be re-aligned for a better street configuration and will create a connection to the existing multi-use pathway at Marian Drive.
A timeline for when phase two will be done has not been confirmed.
Funding Partners
The Town has secured a total of $3.476 million in approved funding from the Government of Canada, the Province of Nova Scotia, and the Municipality of the County of Antigonish. There are additional funding applications pending.
ICIP Funding - East Main to Adam Street - $466,199
Active Transporation Trail, curbs, railway crossing
ICIP Funding - Bay Street - $1,808,400
Water lines, sewer lines, and storm instrastructure
GRID Infrastructure Funding - $1,116,700
Road realignment, raising of the road, and moving utility poles
Municipality of the County of Antigonish - $117,000
Sewer instrastructure
Why is this work being done?
Repairing Infrastructure
The existing municipal services (water and sewar lines) in this corridor are over 100 years old and there was a failed sewer line near Haley Road. The infrastructure is in desperate need of repair and needs an upgrade to increase our capacity to better serve the surrounding community and accommodate future development.
Street Realignment
Bay Street will be realigned street layout for better traffic flow and safer sightlines. In phase one, the elevation of the street was raised to reduce the risk of flooding.
Accessibility
The current sidewalks going up the hill to the hospital entrance has utility poles in the middle of the sidewalk making them inaccessible. These poles will be moved outside of the walkway and the sidewalk will be transformed into a smooth, wider, active transportation trail.
None of the existing pedestrian ramps along Bay Street have tactile warning service indicators. These are a system of textured ground surface indicators to assist people who are visually impaired effectively navigate the environment and indicate where they are entering a traffic area.
Relocating Utility Poles
Several of the utility poles along the Bay Street corridor are located within the sidewalk, which is not convenient for pedestrians and particularly persons with disabilities.
Utility poles should be located off the roadway and sidewalk. These poles will be relocated to the grass boulevard between the roadway and the multi-use pathway for this project.
This Project Includes:
When all phases are complete, Bay Street and the east end of Main Street will have the following upgraded utilities:
- Installation of approximately 520m of new 300mm sanitary main
- Installation of approximately 550m of new 200mm watermain
- Installation of approximately 170m of new storm sewer
- Reconnection of existing services
- Relocation of utility poles
Full Street Recapitalization:
- Upgrades to existing road geometry
- 1200m of new curb
- 810m2 of new sidewalk
- 1450m2 of new active transportation facility
At Grade Rail Crossing Improvements:
- Improved geometry
- Designated pedestrian crossing infrastructure
Bay Street - Project Corridor (1)

Bay Street - Project Corridor (2)

Key Improvements:
- Replacement of over 100-year-old water pipes.
- Reconstruction of a failed sewer main near Tim Hortons.
- Realigned street layout for better traffic flow and safer sightlines.
- New accessible sidewalks and a multi-use Active Transporation trail connecting East Main, Adam Street, and the Hospital.
- Road raising near the river to reduce flood risk.
- Relocation of utility poles outside of walkways.
- Improved connections from the north and east to Downtown and the Landing trail.
Key Features

Map of Project Area

Concept Renderings






